Village of Linglestown Construction Map
Phase 4 March 28th to May 7th
· Traffic will flow one way from East to West on
· Construction will begin on the East half of the roundabout on
· Traffic will flow one way on
Phase 5 May 9th to May 27th
· Traffic will flow in both directions from
· Traffic will continue to flow in one direction from
Phase 6 May 30th to June 13th
· Roundabouts are completed and open.
· Construction on
Post Phase 6 after June 13th
· The top pavement layer will be applied with two way traffic flow using a flagging operation.
Access to Linglestown Life
· If you are travelling from East of Linglestown Square, you will be able to use
· If you are travelling North on
· If you are travelling from West of Linglestown Square, you can turn right at Ranger Road, turn left at Laurel Street, proceed several blocks turning left on Pennsylvania Avenue, then right on Larue, and then turn left on N. Mountain Road.
· Or, if you are travelling from West of Linglestown Square, you can head East on Linglestown Road, turn left at the stop sign at Blue Mountain Parkway, and then turn right onto Blackberry Alley.
Leaving Linglestown Life
· No traffic will be able to exit on
· All traffic leaving Linglestown Life will need to exit via Blackberry Alley.